ROAD TRAFFIC REGULATION ACT 1984 - SECTION 14(1)
Temporary Traffic Regulation Order of Hall Road, Church Street, Crow Street, High Street, Chickney Road, Henham Road, Scotts Farm Lane, Henham

Please click on the following link https://roadworks.org?tm=104167411 to find details of the intended closure of Hall Road, due to commence on 16th February 2018 for 1 day. The closure is required for the safety of the public and workforce whilst Essex County Council undertakes Phase 1 of Surface Dressing works.

The phases of the works are specified below:
Phase 1: Pre-Surface Dressing Works - The crews will patch any potholes and other defects then ensure the surface is made level, some roads will also require further Joint Sealing, Kerb Realignment and Drain/Manhole cover replacement works to take place.
Phase 2: Surface Dressing Works - The crews will spray the existing road surface with a coating of hot bitumen and cover it with stone chippings. The chippings are then rolled into the bitumen to form a water-resistant protective layer which makes the road less slippery and extends its life.
Phase 3: Post Surface Dressing Works - After approximately 7 to 10 days the crews will then return to the road to sweep up any loose chippings that have not been pressed into the bitumen and appropriate road markings will be added.

For more information please click the following link to watch a video about the Surface Dressing process: https://www.youtube.com/watch?v=2dqowi3JXhg

Essex Streetworks Team